The Committee had before it by way of a referral, the minute extract from the City Growth and Resources Committee of 24 April 2018 and the associated report in relation to Shaping Aberdeen Housing LLP.
The decision of that Committee was to approve the following recommendation:
(h) refer the report to the Capital Programme Committee on 23 May 2018, for approval to proceed with the Summerhill site as a Council house build project to deliver 369 homes consisting of 1, 2 and 3 bedroomed flatted apartments for social rent based on the current design proposals and that this be added to the capital programme.
The Committee resolved:-
to approve the recommendation contained in the referred report.