(i)        to accept the contents of the analysis and modelling carried out by the AWPR/BT Technical Advisors, with respect to the anticipated operation and performance of the main AWPR/B-T junctions; and

(ii)       that a Service Update be circulated to members of the Committee and Local Ward Members in relation to the proposals identified by Transport Scotland to mitigate traffic issues at the Kingswells South junction.

Minutes:

With reference to article 32 of the minute of meeting of Council of 15 March 2017, the Committee had before it a report by the Chief Officer – Capital, which provided a robust analysis of the performance of the new AWPR/B-T main junctions which had been undertaken and revealed that there were no significant impacts now that the AWPR/B-T was fully operational.

 

The report recommended:-

that the Committee accept the contents of the analysis and modelling carried out by the AWPR/BT Technical Advisors, with respect to the anticipated operation and performance of the main AWPR/B-T junctions.

 

The Committee resolved:-

(i)        to approve the recommendation; and