Expansion of Early Learning and Childcare – Phase 2 Projects

Meeting: 26/09/2019 - City Growth and Resources Committee (Item 18)

18 Expansion of Early Learning and Childcare – Phase 2 Projects - RES/19/358 pdf icon PDF 90 KB

Decision:

(i)        to approve funding for the delivery of Phase 2 of the Early Learning and Childcare expansion programme in accordance with the principles of the specific Capital Grant award;

(ii)       to delegate authority to the Chief Officer - Capital, following consultation with the Convener of the City Growth and Resources Committee, the Convener of the Capital Programme Committee and the Head of Commercial and Procurement Services, to consider and approve business cases (including estimated expenditures) for the following projects for the purposes of Procurement Regulation 4.1.1:-

·         Cults School – Extension;

·         Culter School – Extension;

·         Kingswells School – Remodel Existing Nursery;

·         Kirkhill School – New Build Nursery;

·         Broomhill School – Extension;

·         Charleston School – Remodel Existing Nursery;

·         Gilcomstoun School – New Build Nursery; and

·         Loirston School – Remodel Existing Nursery; and

(iii)      to thereafter procure appropriate works and services and enter into any contracts necessary for the delivery of the projects subject to due diligence, consistency with the financial model and affordability and regular update on progress against the approved business case at the Capital Programme Committee.

Minutes:

With reference to article 9 of the minute of meeting of the Education and Children’s Services Committee of 14 September 2017, the Committee had before it a report by the Director of Resources which outlined the details of the planned projects within phase 2 of the Early Learning and Childcare expansion programme.

 

The report recommended:-

that the Committee –

(a)       approve funding for the delivery of Phase 2 of the Early Learning and Childcare expansion programme in accordance with the principles of the specific Capital Grant award;

(b)       delegate authority to the Chief Officer - Capital, following consultation with the Convener of the City Growth and Resources Committee, the Convener of the Capital Programme Committee and the Head of Commercial and Procurement Services, to consider and approve business cases (including estimated expenditures) for the following projects for the purposes of Procurement Regulation 4.1.1:-

·         Cults School – Extension;

·         Culter School – Extension;

·         Kingswells School – Remodel Existing Nursery;

·         Kirkhill School – New Build Nursery;

·         Broomhill School – Extension;

·         Charleston School – Remodel Existing Nursery;

·         Gilcomstoun School – New Build Nursery; and

·         Loirston School – Remodel Existing Nursery; and

(c)       thereafter procure appropriate works and services and enter into any contracts necessary for the delivery of the projects subject to due diligence, consistency with the financial model and affordability and regular update on progress against the approved business case at the Capital Programme Committee.

 

The Committee resolved:-

to approve the recommendations.