16 A92 Murcar North - PLA/19/359 PDF 1 MB
Additional documents:
Decision:
(i) to approve the detailed design of the shared use path;
(ii) to delegate authority to Chief Officer – Capital following consultation with the Head of Commercial and Procurement Services, to undertake a tender process for the procurement and thereafter award of a contract;
(iii) to approve the total estimated expenditure of £450,000 as detailed in this report; and
(iv) to instruct the Chief Officer – Operations and Protective Services to undertake the statutory requirements to promote a Redetermination Order to support the successful delivery of the project.
Minutes:
With reference to article 9 of the minute of meeting of 24 April 2018, the Committee had before it a report by the Chief Officer – Strategic Place Planning which sought approval for the construction of a 3 metres wide standard shared-use pedestrian and cycleway north of Aberdeen along the A92 from the Murcar roundabout, Bridge of Don northwards to South Blackdog.
The report recommended:-
that the Committee –
(a) approve the detailed design of the shared use path;
(b) delegate authority to the Chief Officer – Capital following consultation with the Head of Commercial and Procurement Services, to undertake a tender process for the procurement and thereafter award of a contract;
(c) approve the total estimated expenditure of £450,000 as detailed in this report; and
(d) instruct the Chief Officer – Operations and Protective Services to undertake the statutory requirements to promote a Redetermination Order to support the successful delivery of the project.
The Committee resolved:-
to approve the recommendations.