Aberdeen Art Gallery Progress Report
Meeting: 24/03/2021 - Capital Programme Committee (Item 13)
Aberdeen Art Gallery Progress Report - RES/21/066
Decision:
(i) to note the background leading to the current assessment of key contractual dates; and
(ii) to note the current contractual position and planned next steps to reach
settlement with the Contractor and associated financial and reputational risks related to this approach.
Minutes:
The Committee had before it a report by the Director of Resources which provided an update in relation to the on-going contractual and legal process to reach a contract/financial settlement with the appointed Principal Contractor for the main works.
The report recommended:-
That the Committee -
(a) note the background leading to the current assessment of key contractual dates; and
(b) note the current contractual position and planned next steps to reach
settlement with the Contractor and associated financial and reputational risks related to this approach.
The Committee resolved:-
to approve the recommendations contained in the report.