Agenda item

Shielhill Road Mundurno - 131851

Planning Reference – 131851/DPP

 

All documents associated with this application can be found at the following link and enter the above reference number.  https://publicaccess.aberdeencity.gov.uk/online-applications/

 

Planning Officer:  Robert Forbes

Minutes:

The Committee had before it a report by the Chief Officer – Strategic Place Planning, which recommended:-

 

That the application for detailed planning permission for the erection of 99 houses with associated car parking, landscaping and drainage at Shielhill Road Mundurno Aberdeen, be approved subject to a legal agreement and the following conditions:-

 

Conditions

(01)        Path Links

No development shall take place unless a scheme for the provision of proposed footpath / cycle links (together with associated bridge crossings over the Burn of Mundurno), to connect the proposed dwellings with the adjacent housing development under construction to the west of the site, and for provision of footpath and cycle connection to the site from Denmore Road, has been submitted to and approved in writing by the planning authority, or planning permission has been secured for such links. Thereafter none of the dwellings shall be occupied unless the said foot / cycle path links have been implemented in full.

Reason - in the interests of pedestrian / cycle connection and sustainable development.

 

(02)        Site / Plot Boundaries

No development pursuant to this planning permission shall take place, nor shall any part of the development hereby approved be occupied, unless there has been submitted to and approved in writing by the Planning Authority, a detailed scheme of site and plot boundary enclosures for the entire development hereby granted planning permission. The dwellings hereby granted planning permission shall not be occupied unless the required boundaries have been implemented in full, unless the planning authority has agreed to vary such requirements.

Reason - in order to preserve the amenity of the neighbourhood and protect the setting of the green belt / visual approach to the city.

 

(03)        Buffer Strips

No development shall take place pursuant to this planning permission unless a site specific environmental management plan has been submitted to and approved in writing by the planning authority. This shall include site specific details for the protection of the watercourses including detailed site plans showing protection and mitigation proposals, and a site specific plan demonstrating a 6m buffer strip adjacent to all watercourses on site. All buffer strips shall be maintained free of development and construction activity during the construction and implementation of the development and thereafter shall be retained as a vegetated amenity area. No construction activity or development shall take place within buffer strips without the written agreement of the planning authority.

Reason - in order to protect water quality and ecology.

 

(04)        Low Carbon / Water Efficiency

No development shall take place pursuant to this permission unless a scheme detailing compliance with the Council's 'Resources for New Development' supplementary guidance has been submitted to and approved in writing by the planning authority. The buildings hereby approved shall not be occupied unless any recommended measures specified within that scheme for the reduction of carbon emissions and to ensure water efficiency have been implemented in full.

Reason - to ensure that this development complies with requirements for reductions in carbon emissions specified in the City Council's relevant published Supplementary Guidance document, 'Resources for New Development'.

 

(05)         Landscape

No development pursuant to the planning permission hereby approved shall be carried out unless there has been submitted to and approved in writing for the purpose by the planning authority a further detailed scheme of landscaping for the site, which scheme shall include indications of all existing landscape features on the land, and details of any to be retained, together with measures for the protection and translocation of the northern march orchids within the site in the course of development, and the proposed areas of tree/shrub planting including details of numbers, densities, locations, species, sizes and stage of maturity at planting. All planting, seeding and turfing comprised in the approved scheme of landscaping shall be carried out in the first planting season following the completion of the development. Any trees or plants which within a period of 5 years from the completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a size and species similar to those originally required to be planted, or in accordance with such other scheme as may be submitted to and approved in writing for the purpose by the planning authority.

Reason - in the interests of the amenity of the area.

 

(06)        Public Open Space

No dwellings hereby granted planning permission shall be occupied unless the areas of public open space (i.e. softscape, excluding private gardens, as identified on Drawing No.294/ P3 of the plans hereby approved, or such other drawing as may be subsequently approved) have been laid out in accordance with a scheme which shall be submitted to and approved in writing by the Planning Authority. No development pursuant to this planning permission shall take place unless a scheme detailing the manner in which delivery of the open space is to be phased, delivered and maintained has been submitted to and approved in writing by the planning authority. Such scheme shall include provision for a play area comprising at least five items of play equipment and a safety surface.

Reason - in order to preserve the amenity of the neighbourhood.

 

(07)        Flood Risk

No development, including land raising, or temporary construction works / site compounds, shall take place within the functional flood plain as shown on figure 3.4 of the flood risk assessment by Envirocentre, dated December 2013. Finished floor levels for all properties shall be a minimum of 600mm above the design flood level as reported in table 3.2 of the flood risk assessment by Envirocentre, dated December 2013. No development shall take place pursuant to this permission unless a detailed plan showing finished ground levels and floor levels for each property within the development has been submitted to and approved in writing by the planning authority.

Reason - In order to minimise the risk of flooding.

 

(08)        Archaeology

No development shall take place within the application site, other than with the agreement of the planning authority, unless the applicant has secured the implementation of a programme of archaeological work which shall include post-excavation and publication work in accordance with a written scheme of investigation which has been submitted by the applicant and approved by the planning authority.

Reason - in the interests of protecting / recording items of historical importance as may exist within the application site.

 

(09)        Emergency Access

No development shall take place unless a scheme for the provision of an emergency vehicle access route to serve the development and connect with an existing adopted road, has been submitted to and approved in writing by the planning authority. No more than 50 dwelling houses shall be occupied on the site unless the proposed emergency access road as detailed has been provided in accordance with this scheme and is fully operational.

Reason - in the interest of public safety and provision of secondary emergency vehicle access.

 

(10)        Vehicle Charging

No development shall take place pursuant to this permission unless there has been submitted to and agreed in writing by the planning authority a scheme for provision of electric vehicle charging infrastructure for the site. Thereafter none of the dwellings shall be occupied unless the required infrastructure has been implemented for the relevant dwelling.

Reason - in the interests of sustainable development.

 

(11)        Construction Method Statement

No development pursuant to this planning permission shall commence unless a detailed site specific construction method statement for the site has been submitted to and approved in writing by the planning authority. The method statement must address the temporary measures proposed to deal with surface water run-off during construction and prior to the operation of the final SUDS. Such statement shall be implemented in full for the duration of works on the site.

Reason - in order to prevent potential water pollution.

 

(12)        SUDS

No development shall take place unless a scheme of all drainage works designed to meet the requirements of Sustainable Urban Drainage Systems has been submitted to and approved in writing by the Planning Authority and thereafter no part of the development shall be occupied unless the drainage has been installed in complete accordance with the said scheme.

Reason - in order to safeguard water qualities in adjacent watercourses and to ensure that the development can be adequately drained.

 

(13)        Noise Mitigation

The dwellings hereby approved shall not be occupied unless the required noise mitigation measures, as detailed in the approved noise assessment have been implemented in full (for each individual building), unless the planning authority has given prior written approval for a variation.

Reason - in the interests of residential amenity.

 

(14)        Play Area

No dwelling hereby granted planning permission shall be occupied unless a Children’s Play Area is completed, laid out and equipped as a play area in accordance with a scheme that has been approved in writing for the purpose by the Planning Authority, unless the planning authority has given prior written approval for a variation. The said area shall not thereafter be used for any purpose other than as a play area.

Reason - in order to ensure the timeous provision of play facilities.

 

(15)        Foul Drainage

The dwellings hereby granted planning permission shall not be occupied unless a scheme for the connection to the public sewerage network has been submitted to and approved in writing by the Planning Authority and that the said scheme has been implemented.

Reason - in the interests of public health and pollution prevention.

 

(16)        Car Parking

The dwellings hereby approved shall not be occupied unless provision has been made within the site for the off-street parking of motor vehicles for the specific dwellings in complete accordance with Plan No.A5143/P12C, or such other scheme as may be subsequently approved in writing by the planning authority.

Reason - in the interests of road safety and the free flow of traffic.

 

The Committee heard from Robert Forbes, Senior Planner, who spoke in furtherance of the application and answered various questions from members, which included whether there was sufficient capacity at the local primary school and Academy, the health care provision for the area and also the drainage impact assessment.

 

The Committee resolved:-

to approve the recommendation and therefore approve the application conditionally with a legal agreement, with a revised condition 12 for SUDS and also an extra condition at 17 in regards to public open space maintenance, which would read:-

 

(12)     SUDS

No development shall take place pursuant to this planning permission unless a drainage impact assessment and scheme of all drainage works for the site, designed to meet the requirements of Sustainable Urban Drainage Systems, has been submitted to and approved in writing by the Planning Authority. Thereafter no part of the development shall be occupied unless the drainage works on site have been installed in complete accordance with the said scheme.

Reason - in order to safeguard water qualities in adjacent watercourses and to ensure that the development can be adequately drained.

 

(17)        Public Open Space Maintenance

No dwelling hereby granted planning permission shall be occupied unless a scheme for the maintenance of the public open space areas within the development site (i.e. softscape, excluding private gardens, as identified on Drawing No.294/ P3 of the plans hereby approved, or such other drawing as may be subsequently approved), has been submitted to and  approved in writing by the Planning Authority, unless the planning authority has given prior written approval for a variation.   No dwelling shall be occupied unless the open space is maintained in accordance with the approved scheme.

Reason  – in the interest of protection of residential amenity and compliance with Aberdeen City Council Supplementary Guidance regarding Green Space Network and Open Spaces and Green Infrastructure.

 

Supporting documents: