Torry Heat Network - Third Progress Report - RES/20/172

Decision Maker: City Growth and Resources Committee

Decision status: For Determination

Is Key decision?: No

Is subject to call in?: No

Decision:

(i)       to approve the proposed amended scope for this phase of this project;

(ii)       to approve the acceptance of a Low Carbon Infrastructure Programme Grant from the Scottish Government;

(iii)      to approve the carry forward of any portion of the General Fund Capital budget for the project, not required for this phase of works, so that it can be used as match-funding against a future grant application;

(iv)      to approve the Council entering into a twenty year Heat Offtake agreement with the EfW operating company which follows the principles set out in appendix 10.3, and approves the estimated annual expenditure associated therewith set out in appendix 10.1; and

(v)      to approve the recommendations contained within section 3.2 of this report with regard to the upgrading and usage of the Council’s assets, property and estates.

Publication date: 03/11/2020

Date of decision: 28/10/2020

Decided at meeting: 28/10/2020 - City Growth and Resources Committee