Issue - meetings
Bus Lane Enforcement Update
Meeting: 25/04/2019 - City Growth and Resources Committee (Item 10)
10 Bus Lane Enforcement Programme Update & Future Planning 2019/20 - PLA/19/226 PDF 103 KB
Additional documents:
- PLA 19 226 Final Appendix 1 Bus Lane Enforcement Fund 1920, item 10 PDF 83 KB
- PLA 19 226 Final Appendix 2 Bus Lane Enforcement 2019, item 10 PDF 59 KB
Decision:
(i) to note the progress on the projects funded from the BLE programme up to 2018/19, as detailed in Appendix 1;
(ii) to approve the request to treat as high priority and release funding when it becomes available for the temporary traffic management for Offshore Europe 2019 as detailed Appendix 2;
(iii) to approve the request to commit BLE funding to Offshore Europe (when in Aberdeen) for the amount of up to £60,000 providing there is available BLE funding; and
(iv) to agree not to currently seek any further new applications for the BLE
programme and continue with the delivery of the current BLE programme.
Minutes:
With reference to article 7 of the minute of meeting of the Strategic Commissioning Committee of 30 April 2018, the Committee had before it a report by the Chief Officer – Strategic Place Planning, which (1) provided an update on the status of the current Bus Lane Enforcement (BLE) programme; (2) sought approval for funding to be released for the Traffic Management of Offshore Europe 2019; and (3) requested approval to not seek any further new BLE applications until the programme is completed.
The report recommended:-
that the Committee –
(a) note the progress on the projects funded from the BLE programme up to 2018/19, as detailed in Appendix 1;
(b) approve the request to treat as high priority and release funding when it becomes available for the temporary traffic management for Offshore Europe 2019 as detailed Appendix 2;
(c) approve the request to commit BLE funding to Offshore Europe (when in Aberdeen) for the amount of up to £60,000 providing there is available BLE funding; and
(d) agree not to currently seek any further new applications for the BLE
programme and continue with the delivery of the current BLE programme.
The Committee resolved:-
to approve the recommendations.