A90 Murcar North Cycleway

Meeting: 05/12/2019 - City Growth and Resources Committee (Item 16)

16 A92 Murcar North - PLA/19/359 pdf icon PDF 1 MB

Additional documents:

Decision:

(i)        to approve the detailed design of the shared use path;

(ii)       to delegate authority to Chief Officer – Capital following consultation with the Head of Commercial and Procurement Services, to undertake a tender process for the procurement and thereafter award of a contract;

(iii)      to approve the total estimated expenditure of £450,000 as detailed in this report; and

(iv)      to instruct the Chief Officer – Operations and Protective Services to undertake the statutory requirements to promote a Redetermination Order to support the successful delivery of the project.

Minutes:

With reference to article 9 of the minute of meeting of 24 April 2018, the Committee had before it a report by the Chief Officer – Strategic Place Planning which sought approval for the construction of a 3 metres wide standard shared-use pedestrian and cycleway north of Aberdeen along the A92 from the Murcar roundabout, Bridge of Don northwards to South Blackdog.

 

The report recommended:-

that the Committee –

(a)       approve the detailed design of the shared use path;

(b)       delegate authority to the Chief Officer – Capital following consultation with the Head of Commercial and Procurement Services, to undertake a tender process for the procurement and thereafter award of a contract;

(c)       approve the total estimated expenditure of £450,000 as detailed in this report; and

(d)       instruct the Chief Officer – Operations and Protective Services to undertake the statutory requirements to promote a Redetermination Order to support the successful delivery of the project.

 

The Committee resolved:-

to approve the recommendations.