Issue - meetings
Bus Lane Enforcement Fund Refresh -
Meeting: 10/11/2021 - City Growth and Resources Committee (Item 12)
12 Bus Lane Enforcement Fund Refresh - COM/21/253 PDF 247 KB
Additional documents:
- BLE App 1, item 12 PDF 102 KB
- BLE App 2, item 12 PDF 145 KB
- BLE App 3, item 12 PDF 283 KB
- BLE App 4 simplified, item 12 PDF 110 KB
Decision:
(i) note the progress on the projects funded from the Bus Lane Enforcement programme up to 2021/22, as detailed in Appendix 1;
(ii) note that Council priorities have evolved since the Bus Lane Enforcement programme was last open to funding bids in 2018/19;
(iii) instruct the Chief Officer – Strategic Place Planning to refresh the BLE programme for the 2022/23 financial year and beyond in terms of the Council’s current priorities, as noted in 3.4 and 3.6, and report this to a future meeting of this Committee;
(iv) agree that the current programme of legacy projects, as detailed in Appendix 2, should be completed before any new projects are progressed;
(v) agree to continue to fund the transport officer post as described in paragraph 3.8 to ensure continued management and compliance;
(vi) agree to the use of the application form, as detailed in Appendix 3, for all new Bus Lane Enforcement projects; and
(vii) note the Governance process for Bus Lane Enforcement projects, as detailed in Appendix 4.
Minutes:
The Committee had before it a report by the Director of Commissioning which provided an update on the status of the current Bus Lane Enforcement programme and sought approval for the programme to be refreshed with a new application process that better meets current Council priorities.
The report recommended:-
that the Committee –
(a) note the progress on the projects funded from the Bus Lane Enforcement programme up to 2021/22, as detailed in Appendix 1;
(b) note that Council priorities have evolved since the Bus Lane Enforcement programme was last open to funding bids in 2018/19;
(c) instruct the Chief Officer – Strategic Place Planning to refresh the BLE programme for the 2022/23 financial year and beyond in terms of the Council’s current priorities, as noted in 3.4 and 3.6 (of the report), and report this to a future meeting of this Committee;
(d) agree that the current programme of legacy projects, as detailed in Appendix 2, should be completed before any new projects are progressed;
(e) agree to continue to fund the transport officer post as described in paragraph 3.8 (of the report) to ensure continued management and compliance;
(f) agree to the use of the application form, as detailed in Appendix 3, for all new Bus Lane Enforcement projects; and
(g) note the Governance process for Bus Lane Enforcement projects, as detailed in Appendix 4.
The Committee resolved:-
to approve the recommendations.