Cruyff Court Tillydrone Update - RES/23/199
Meeting: 05/07/2023 - Finance and Resources Committee (Item 15)
15 Cruyff Court Tillydrone Update - RES/23/199 PDF 229 KB
An exempt appendix relating to this report is contained within the Exempt Appendices Section of this agenda.
Decision:
(i) vire the necessary monies from the budget savings following the retender of the Replacement Riverbank Primary School project (noted previously as circa £6m) to ensure the full scope of the project can be delivered; and
(ii) instruct the Chief Officer - Capital to complete a further procurement exercise to target delivery this financial year.
Minutes:
The Committee had before it a report by the Director of Resources which sought approval to progress with the Tillydrone Cruyff Court project subject to additional funding.
The report recommended:-
that the Committee –
(i) vire the necessary monies from the budget savings following the retender of the Replacement Riverbank Primary School project (noted previously as circa £6m) to ensure the full scope of the project can be delivered; and
(ii) instruct the Chief Officer - Capital to complete a further procurement exercise to target delivery this financial year.
The Committee resolved:-
to approve the recommendations.