The Committee resolved:-

to approve the Occupational Health and Safety Service Plan for 2024/25 at Appendix 1.

Minutes:

The Committee had before it a report by the Interim Chief Officer – Governance (Legal) which outlined the Protective Services proposals for delivering the occupational safety and health regulatory service for year 2024/2025. 

 

The report recommended:-

that the Committee approve the Occupational Health and Safety Service Plan for 2024/25 at Appendix 1.

 

The Committee resolved:-

to approve the recommendation. 

 


Meeting: 28/03/2024 - Communities, Housing and Public Protection Committee (Item 11)

11 New Housing Capital Programme Delivery Projects Update - RES/24/096 pdf icon PDF 3 MB

Decision:

The Committee resolved:-

(i)             notes the progress to deliver the programme of social housing sites across the city; and

(ii)            to request that the Chief Officer – Capital, liaise with the contractor for the works at 206 Union Street into possible advertising on the scaffolding.

Minutes:

The Committee had before it a report by the Chief Officer – Capital, which  summarised the general progress of delivery of key capital expenditure projects identified within the approved Capital Programme from the Housing Revenue Accounts.  

 

The report also highlighted matters considered worthy of particular note in relation to Council led new build housing sites at Summerhill, Craighill, Kincorth, Tillydrone, Kaimhill, Greenferns and Greenferns Landward and the Developer led new build housing site at Cloverhill.

 

The report recommended:-

that the Committee notes the progress to deliver the programme of social housing sites across the city.

 

The Committee resolved:-

(i)             to request that the Chief Officer – Capital, liaise with the contractor for the works at 206 Union Street into possible advertising on the scaffolding; and