Castlegate Refurbishment - Full Business Case

Meeting: 07/08/2024 - Finance and Resources Committee (Item 21)

21 Castlegate Public Realm Update - CR&E/24/219 pdf icon PDF 227 KB

Additional documents:

Decision:

instruct the Chief Officer - Capital to develop the detailed and technical design for the Castlegate element of the City Centre Masterplan Streetscape programme and, following consultation with the Chief Officer – Commercial & Procurement Services, proceed with the negotiation and execution of contracts for delivery of the construction programme in line with the previously approved total project budget as detailed in paragraph 4.1, reporting progress through the Chief Officer – Capital’s regular capital programme monitoring reports.

Minutes:

With reference  to article 3 of the minute of the meeting of the Council of 8 February 2024, the Committee had before it a report by the Director of City Regeneration and Environment which provided an update on the programme for redeveloping the public realm in the Castlegate.

 

The report recommended:-

that the Committee instruct the Chief Officer - Capital to develop the detailed and technical design for the Castlegate element of the City Centre Masterplan Streetscape programme and, following consultation with the Chief Officer – Commercial & Procurement Services, proceed with the negotiation and execution of contracts for delivery of the construction programme in line with the previously approved total project budget as detailed in paragraph 4.1, reporting progress through the Chief Officer – Capital’s regular capital programme monitoring reports.

 

The Committee resolved:-

to approve the recommendation.