How can we help you...

Issue - meetings

Ferryhill School/Harlaw Academy Update Report - CR&E/25/

Meeting: 06/08/2025 - Finance and Resources Committee (Item 14)

14 Ferryhill School and Harlaw Academy Suitability Improvements - CR&E/25/173 pdf icon PDF 199 KB

Decision:

(a)      note the advance and enabling development works undertaken to date to reduce risk to the main construction works and mitigate educational disruption;

(b)      note that the works carried out to date remain within the Capital Plan budget envelope and that work continues towards collating the main costs that will allow completion of the full business case; and

(c)      instruct the Chief Officer – Capital to continue to progress all necessary procurements, approvals, permissions, licenses, agreements and consents required to develop and implement the projects within the Capital Programme budget, reporting progress through the regular capital programme monitoring reports to this committee and to circulate for information the full business Cases for each project to committee members once completed; and

(d)      to note that the Director of City Regeneration and Environment would raise Councillor Watson’s concerns regarding the speeding buses on Caledonian Place at the next meeting of the Aberdeen Bus Partnership, which includes within its membership, representation from FirstBus.

Minutes:

With reference to article 3 of the minute of meeting of Council of 5 March 2025, the Committee had before it a report by the Executive Director of City Regeneration and Environment which provided an update on progress and confirmed future reporting arrangements for Ferryhill School and Harlaw Academy Suitability projects identified within the approved Capital Programme.

 

The report recommended:-

that the Committee –

(a)      note the advance and enabling development works undertaken to date to reduce risk to the main construction works and mitigate educational disruption;

(b)      note that the works carried out to date remain within the Capital Plan budget envelope and that work continues towards collating the main costs that will allow completion of the full business case; and

(c)      instruct the Chief Officer – Capital to continue to progress all necessary procurements, approvals, permissions, licenses, agreements and consents required to develop and implement the projects within the Capital Programme budget, reporting progress through the regular capital programme monitoring reports to this committee and to circulate for information the full business Cases for each project to committee members once completed.

 

The Committee resolved:-

(i)       to approve the recommendations contained within the report; and

(ii)      to note that the Director of City Regeneration and Environment would raise Councillor Watson’s concerns regarding the speeding buses on Caledonian Place at the next meeting of the Aberdeen Bus Partnership, which includes within its membership, representation from FirstBus.