Issue - decisions

A90 Murcar North Cycleway

10/12/2019 - A92 Murcar North - PLA/19/359

(i)        to approve the detailed design of the shared use path;

(ii)       to delegate authority to Chief Officer – Capital following consultation with the Head of Commercial and Procurement Services, to undertake a tender process for the procurement and thereafter award of a contract;

(iii)      to approve the total estimated expenditure of £450,000 as detailed in this report; and

(iv)      to instruct the Chief Officer – Operations and Protective Services to undertake the statutory requirements to promote a Redetermination Order to support the successful delivery of the project.