Berryden Corridor Active Travel Connections - RES/22/177

26/09/2022 - Berryden Corridor Active Travel Connections - RES/22/177

(i)       notes the contents of the business case for the Ashgrove Connects project;

(ii)       agrees the recommendations within the business case for the Ashgrove Connects project appended to this report;

(iii)      instructs the Chief Officer – Strategic Place Planning to submit a bid to Scottish Government’s Places for Everyone scheme for funding to enable the detailed design of the Ashgrove Connects project and implementation, and to circulate a Service Update to members of the Committee on securing match funding;

(iv)      notes the content of the Skene Square to City Centre route option assessment report;

(v)      agrees the preferred option within the Skene Square to City Centre route option assessment report and instructs the Chief Officer - Capital to progress the development of detailed design and, subject to 2.6, its implementation concurrently with the Berryden Corridor Improvement project;

(vi)      instructs the Chief Officer - Capital as part of the detailed design to develop a detailed estimate for the Skene Square to City Centre active travel connection project (being the preferred option as described in the Skene Square to City Centre route option assessment report) and if required, refer any additional funding requirement to this year’s budget process;

(vii)     instructs the Chief Officer - Capital to progress all necessary approvals, permissions, licenses, agreements, and consents required to develop and implement the Ashgrove Connects & Skene Square to City Centre active travel connection projects;

(viii)    delegates authority to the Chief Officer – Capital, following consultation with the Head of Commercial and Procurement Services, to consider and approve business cases (including estimated expenditures) for the Ashgrove Connects and Skene Square to City Centre active travel connection projects for the purposes of Procurement Regulation 4.1.1.2 and 4.1.1.4; thereafter to procure appropriate works and services, and enter into any contracts necessary for the delivery of the projects;

(ix)      notes the recommendation at page 145 of the agenda, “Progress is made towards a comprehensive strategic network study to provide a city-wide plan prioritising active travel routes for future development. This process would benefit from targeted engagement that would greatly enhance and enrich the network planning process along with further data collection and auditing.”; and instructs the Chief Officer – Strategic Place Planning to circulate a Service Update to members of the Committee which sets out the requirements and timescales required to prepare a Strategic Network Study to provide a city-wide active travel priority plan;

(x)      notes ongoing work to progress the A944/A9119 multi-modal study and instructs the Chief Officer – Strategic Place Planning to ensure that this study fully considers, when the relevant report is prepared for committee, the linkages with the Ashgrove Connects scheme and wider Berryden Corridor Active Travel Connections; and

(xi)      instructs the Chief Officer - Capital to provide Service Updates to members of the Committee (as appropriate) on progress relating to recommendation 2.3, 2.5 and 2.7.