Issue - decisions
Outline Business Case: New Secondary School Provision for Hazlehead and Countesswells - RES/23/366 - Finance and Resources Committee of 22 November 2023
20/12/2023 - Outline Business Case: New Secondary School Provision for Hazlehead and Countesswells - RES/23/366 - Finance and Resources Committee of 22 November 2023
The Council resolved:-
(i) to approve in principle the recommended option within the OBC to construct a new 1,600 pupil campus on the current Hazlehead Academy playing fields to provide secondary school provision for Hazlehead and Countesswells ASGs, subject to the outcome of a statutory consultation;
(ii) instruct the Chief Officer - Capital to refer the proposals for the project to the Budget process in 2024/25; and
(iii) subject to the outcomes of the statutory consultation and any decision taken at the budget meeting of March 2024, to approve in principle the use of resources for the implementation of the project from 2024.